-Ive called this meeting to try to find out why were having a difficult time upgrading our EDP [Electronic Data Processing] Department to an MIS [Management Information
Systems] Division,- remarked Bryan Bedford, executive vice president of BBs Consulting.
-Last year we decided to give the EDP Department a chance to show that it could contribute to corporate profits by removing the departmentfrom under the control of the Finance Division and establishing an MIS Division. The MIS Division should be a project-driven division using a project management methodology. I expected great results. I continuously get reports stating that we re having major conflicts and personality clashes among the departments involved in these MIS projects and that we re between one month to three months behind on almost all projects. Ifwe don t resolve this problem right now, the MIS Division will be demoted to a department and once again find itselfunder thejurisdiction ofthefinance director
BACKGROUND
In June 1987, Bryan Bedford announced that BB Consulting would be giving salary increases amounting to an average of 7 percent companywide, with the percent distribution as shown in Exhibit I. The EDP Department, especially the scientific programmers, were furious because this was the third straight year, they had received below-average salary increases. The scientific programmers felt that they were performing engineering-type work and, therefore, should be
paid according to the engineering pay scale. In addition, the software that was developed by the scientific programmers was shortening schedules and lowering manufacturing costs. The scientific programmers saw themselves as contributing to corporate profitability.
The year before, the scientific programmers had tried to convince management that engineering needed its own computer and that there should be established a separate engineering computer programming department within the Engineering Division. This suggestion had strong support from the engineering community because they would benefit by having complete control of their own computer. Unfortunately, management rejected the idea, fearing that competition and conflict would develop by having two data processing units, and that one centralized unit was the only viable solution.
As a result of managements decision to keep the EDP Department intact and not give them a chance to demonstrate that they can and do contribute to profits, the EDP personnel created a closed shop environment and developed a very hostile attitude toward all other departments, even those within their own Finance Division.
THE MEETING OF THE MINDS
In January 1988, Mr. Bedford announced the organizational restructuring that would upgrade the EDP Department. Rory Smith, the EDP Department manager, was given a promotion to division manager, provided that he could adequately manage the MIS project activities. By December 1988, it became apparent that something must be done to remedy the deteriorating relationship between the functional departments and the MIS personnel. Bryan called a meeting of all functional and divisional managers in hopes that some of the problems could be identified and worked out.
Bryan Bedford: -For the past ten months Ive watched you people continuously arguing back and forth about the MIS problems, with both sides always giving me the BS about how well work it out. Now, before its too late, lets try to get at the root cause of the problem.
Anyone want to start the ball rolling?-
Cost accounting manager: -The major problem, as I see it, is the lack of interpersonal skills employed by the MIS people. Our MIS personnel have received only on-the-job training.
The Human Resources Department has never provided us with any project management training, especially in the behavioral areas of project management. Our organization here is, or should I say has been up to now, purely traditional, with each person reporting to and working for and with one manager. Now we have horizontal projects in which the MIS project leaders must work with several functional managers, all of whom have different management styles, different personalities, and different dispositions. The MIS group just cant turn around in one or two weeks and develop these necessary skills. It takes time and training.-
Training manager: -I agree with your comments. There are two types of situations that literally demand immediate personnel development training. The first situation is when personnel are required to perform in an organizational structure that has gone from the relatively simple, pure structure to a complex, partial matrix structure. This is what has happened to us.
The second situation is when the task changes from simple to complex.
-With either situation by itself, there is usually some slack time. But when both occur almost instantaneously, as is our case, immediate training should be undertaken. I told this to
Rory several times, but it was like talking to deaf ears. All he kept saying was that we dont have time now because were loaded down with priority projects.-
Rory Smith: -I can see from the start that were headed for a rake-Rory-over thecoals meeting. So let me defend each accusation as it comes up. The day Bryan announced the organizational change, I was handed a list of fifteen MIS projects that had to be completed within unrealistic time schedules. I performed a manpower requirements projection and found that we were understaffed by 35 percent. Now Im not stupid. I understand the importance of training my people. But how am I supposed to release my people for these training sessions when I have been given specific instructions that each of these fifteen projects had a high priority? I can just see myself walking into your office, Bryan, telling you that I want to utilize my people only half-time so that they can undergo professional development training.-
Bryan Bedford: -Somehow I feel that the buck just got passed back to me. Those schedules that I gave you appeared totally realistic to me. I just cant imagine any simple computer program requiring more time than my original estimates. And had you come to me with a request for training, I would have checked with personnel and then probably would give you the time to train your people.-
Engineering manager: -I wish to make a comment or two about schedules. Im not happy when an MIS guy walks into my office and tells me, or should I say demands, that certain resources be given to him so that he can meet a schedule or milestone date that Ive had no input into establishing. My people are just not going to become pawns in the power struggle for MIS supremacy. My people become very defensive if theyre not permitted to participate in the planning activities, and I have to agree with them.-
Manufacturing manager: -The Manufacturing Division has a project with the MIS group for purchasing a hardware system that will satisfy our scheduling and material handling system requirements. My people wanted to be involved in the hardware selection process. Instead, the MIS group came to us with proposal in hand identifying a system that was not a practical extension of the state of the art and that did not fall within our cost and time constraints. -We in manufacturing, being nice guys, modified our schedules to be compatible with the MIS project leaders proposal. We then tried to provide more detailed information for the MIS team so that . . .
Rory Smith: -Just a minute here! Your use of the word -we- is somewhat misleading. Project management is designed and structured so that sufficient definition of work to be performed can be obtained in order that a more uniform implementation can result. My people requested a lot of detailed information from your staff and were told to do the work ourselves and find our own information. After all, as one of the functional employees put it, if were going to pass all of the responsibility over to you guys in project management; you people can just do it all.
-Therefore, because my people had insufficient data, between us we ended up creating a problem, which was further intensified by a lack of formal communication between the MIS group and the functional departments, as well as between the functional departments themselves. I hold functional management responsible for this problem because some of the managers did not seem to have understood that they are responsible for the project work under their cognizance. Furthermore, I consider you, the manufacturing manager, as being remiss in your duties by not reviewing the performance of our personnel assigned to the project. -
Manufacturing manager: -Your people designed a system that was way too complex for our needs. Your people consider this project as a chance for glory. It is going to take us ten years to grow into this complex system youve created.-
Rory Smith: -Let me make a few comments about our delays in the schedule. One of our projects was a six-month effort. After the third month, there was a new department manager assigned in the department that was to be the prime user of this project. We were then given a change in user requirements and incurred additional delays in waiting for new user authorization.
-Of course, people problems always affect schedules. One of my most experienced people became sick and had to be replaced by a rookie. In addition, Ive tried to be a good guy by letting my people help out some of the functional managers when non-MIS problems occur.
This other work ended up encroaching on staff time to a degree where it impacted the schedules.
-Even though the MIS group regulates computer activities, we have no control over computer downtime or slow turnabout time. Turnabout time is directly proportional to our priority lists, and we all know that these lists are established from above.
Exhibit 1.
Bedfords Organizational Chart. Note: Percentages indicate 1987 salary increases
-And last, we have to consider both company and project politics. All the MIS group wanted to do was to show that we can contribute to company profits. Top management consistently tries to give us unwanted direction and functional management tries to sabotage our projects for fear that if were successful, then it will be less money for their departments during promotion time.-
Bryan Bedford: -Well, I guess weve identified the major problem areas. The question remaining is: What are we going to do about it?-
CASE QUESTIONS
l. What are the major problems in the case study?
2. Was the company committed to project management?
3. Was project management forced upon the organization?
4. Did Bryan Bedford jump blindly into project management, or was there a gradual introduction?
5. Did the company consider the problems that could manifest themselves with the implementation of change (i.e., morale)?
6. Did the company have a good definition of project management?
7. How were project deadlines established?
8. Who established responsibilities for resource management?
9. Can Rory function effectively as both a project manager and a division manager?
10. Did anyone consider employee performance evaluations?
I l. Rory decides to use the network plan shown in Figure I below for a part of the MIS project,
a. compute the early, late, and slack times.
a. What is the project duration?
b. Using any approach you wish (e.g. trial and error) develop a loading chart for resources; Coder (C) and Software Writer (SW). Assume only one Coder is available and two Software Writers are available.
c. Given your resource schedule, compute the early, late, and slack times for your project.
d. Which activities are now critical?
e. What is the new project duration?
Please respond to the questions in an Essay format using APA style of writing. Remember to convert all the questions to titles and subtitles in consonance with the APA style of writing. Make sure to connect issues in the case to concepts and theories in our project management course and make references to the PMBOK and course textbook as much as possible. Provide proper citations and references as required. Make as much assumptions as possible so that your response to the case questions would be very clear to the reader with inputs, techniques, tools and outputs. Submit your assignment to email address: camponsah@fdu.edu by
December 03, 2021, before 12 noon. Late submissions will not be accepted
Figure 1: Rorys Partial Network Plan
3 2
LEGEND
ES ID
SL SL
C- CODER RES
SW-S0ftware Writer DU
RES- RESOURCE
DUR IN WEEKS