Recent Question/Assignment

This quiz covers the material in All Chapters of the text and within the -Insights Documents-. The totality of what you have learned through the course will be needed to successfully answer the questions within the -Scenarios- provided in this Final Exam.
Flag question: Question 1
Question 12 pts
By looking at Page 1 of Scenario 1, how many -unique resources- are assigned to the -actionable tasks-? (Hint: Don't count the number of -tasks- and don't count any resource more than once.)
Group of answer choices
10
15
6
8
Flag question: Question 2
Question 22 pts
By looking at Page 3 of Scenario 2, how many -actionable tasks- that are NOT ON the critical path ARE IN alignment with the baseline?
Group of answer choices
1
3
4
2
Flag question: Question 3
Question 32 pts
By looking at Page 2 of Scenario 1, which resource COSTS the least on the total project?
Group of answer choices
Driver 3
QA 2
QC 3
Analyst 1
Analyst 2
Driver 1
QC 2
Project Admin
Driver 2
Designer 1
Project Mgr
Designer 2
QC 1
QA 1
QA 3
Flag question: Question 4
Question 42 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have a -Finish to Finish- relationship with another task?
Group of answer choices
1
3
2
4
Flag question: Question 5
Question 52 pts
By looking at Page 3 of Scenario 2, and comparing it to Page 2 of Scenario 2, is the OVERALL project MORE over budget or under budget, LESS over budget or under budget, or at the same -budget indication- as on Page 2 of Scenario 2?
Group of answer choices
It cannot be determined
Less over or under budget
Same indication as on Page 2
More over or under budget
Flag question: Question 6
Question 62 pts
By looking at Page 2 of Scenario 2, is the OVERALL project currently over budget [spending too much], under budget [spending too little] or on budget.
Group of answer choices
On budget
It cannot be determined
Over budget
Under budget
Flag question: Question 7
Question 72 pts
By looking at Page 1 of Scenario 2, how many UNIQUE resources have -actionable tasks- that they are assigned to that are NOT ON the critical path? (HINT: don't count the tasks, and don't count any resource more than once.)
Group of answer choices
2
5
3
4
Flag question: Question 8
Question 82 pts
By looking at Page 2 of Scenario 1, which is the MOST expensive phase of the project?
Group of answer choices
Executing Activities
It cannot be determined
Monitoring & Controlling
Executing
Closing Activities
Planning
Initiating
Initiating Activities
Closing
Planning Activities
Flag question: Question 9
Question 92 pts
By looking at Page 2 of Scenario 1, which resource does the LEAST amount of work?
Group of answer choices
Project Mgr
QC 2
Driver 3
Analyst 2
QA 2
Designer 1
QA 3
QA 1
Driver 2
QC 1
Driver 1
Designer 2
Project Admin
Analyst 1
QC 3
Flag question: Question 10
Question 102 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have multiple predecessors?
Group of answer choices
3
1
2
4
Flag question: Question 11
Question 112 pts
By looking at Page 3 of Scenario 2, how many -actionable tasks- that are ON the critical path are NOT in alignment with the baseline?
Group of answer choices
3
1
2
0
Flag question: Question 12
Question 122 pts
By looking at Page 2 of Scenario 1, which resource COSTS the most on the total project?
Group of answer choices
Driver 1
Designer 2
Driver 3
Driver 2
Designer 1
QA 3
Project Admin
QA 1
Project Mgr
QA 2
QC 1
Analyst 1
QC 3
Analyst 2
QC 2
Flag question: Question 13
Question 132 pts
By looking at Page 2 of Scenario 1, which phase of the project is the LEAST number of days?
Group of answer choices
Executing
Monitoring & Controlling
Initiating
Closing Activities
Closing
Planning Activities
Planning
Initiating Activities
Executing Activities
It cannot be determined
Flag question: Question 14
Question 142 pts
By looking at Page 1 of Scenario 2, how many -actionable tasks- are NOT ON the critical path and have made some progress?
Group of answer choices
5
2
3
4
Flag question: Question 15
Question 152 pts
By looking at Page 3 of Scenario 2, and comparing it to Page 2 of Scenario 2, is the OVERALL project MORE ahead or behind schedule, LESS ahead or behind schedule, or at the same -schedule indication- as on Page 2 of Scenario 2?
Group of answer choices
Same indication as on Page 2
Less ahead or behind schedule
It cannot be determined
More ahead or behind schedule
Flag question: Question 16
Question 162 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have multiple resources assigned?
Group of answer choices
5
2
3
7
Flag question: Question 17
Question 172 pts
By looking at Page 2 of Scenario 1, how many resources are NOT OVER ALLOCATED?
Group of answer choices
15
12
10
It cannot be determined
Flag question: Question 18
Question 182 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- that are NOT on the critical path have a resource assigned that is fully utilized (HINT: is working at 100%).
Group of answer choices
6
10
8
12
Flag question: Question 19
Question 192 pts
By looking at Page 2 of Scenario 2, is the OVERALL project currently ahead of schedule, behind schedule, or on schedule?
Group of answer choices
Ahead of Schedule
It cannot be determined
Behind Schedule
On Schedule
Flag question: Question 20
Question 202 pts
By looking at Page 2 of Scenario 1, how many resources have the same -total cost- on the project?
Group of answer choices
2
3
4
It cannot be determined
Flag question: Question 21
Question 212 pts
By looking at Page 3 of Scenario 1, how many UNIQUE resources have -actionable tasks- that they are assigned to that are NOT ON the critical path? (HINT: don't count the tasks, and don't count any resource more than once.)
Group of answer choices
3
4
2
1
Flag question: Question 22
Question 222 pts
By looking at Page 2 of Scenario 1, how many resources are the least expensive, based on their -Standard Hourly- rate?
Group of answer choices
3
6
5
4
Flag question: Question 23
Question 232 pts
By looking at Page 2 of Scenario 2, how many -actionable tasks- that are NOT ON the critical path are now NOT in alignment with the baseline?
Group of answer choices
1
4
2
0
3
Flag question: Question 24
Question 242 pts
By looking at Page 3 of Scenario 2, how many -actionable tasks- that are ON the critical path ARE IN alignment with the baseline?
Group of answer choices
2
3
1
4
Flag question: Question 25
Question 252 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have a -Start to Start- relationship with another task?
Group of answer choices
2
4
1
3
Flag question: Question 26
Question 262 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- that are on the critical path have a resource assigned that is NOT fully utilized (HINT: not working at 100%).
Group of answer choices
1
2
3
4
Flag question: Question 27
Question 272 pts
By looking at Page 3 of Scenario 2, how many -actionable tasks- that are NOT ON the critical path are NOT in alignment with the baseline?
Group of answer choices
4
3
1
2
Flag question: Question 28
Question 282 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- are on the critical path [HINT: Milestone tasks are also on the critical path].
Group of answer choices
5
15
7
12
Flag question: Question 29
Question 292 pts
By looking at Page 1 of Scenario 2, how many -actionable tasks- are showing progress but are still considered -behind schedule-?
Group of answer choices
4
1
3
2
Flag question: Question 30
Question 302 pts
By looking at Page 2 of Scenario 1, how many resources are OVER ALLOCATED?
Group of answer choices
2
In cannot be determined
4
3
Flag question: Question 31
Question 312 pts
By looking at Page 1 of Scenario 2, how many -actionable tasks- are showing progress but considered -ahead of schedule-?
Group of answer choices
1
2
4
3
Flag question: Question 32
Question 322 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- that are on the critical path have a resource assigned that is fully utilized (HINT: is working at 100%).
Group of answer choices
4
1
2
3
Flag question: Question 33
Question 332 pts
By looking at Page 1 of Scenario 2, is the OVERALL project currently over budget [spending too much], under budget [spending too little] or on budget.
Group of answer choices
Over Budget
On Budget
It cannot be determined
Under Budget
Flag question: Question 34
Question 342 pts
By looking at Page 1 of Scenario 2, how many -actionable tasks- are ON the critical path and are NOT completed?
Group of answer choices
3
5
2
4
Flag question: Question 35
Question 352 pts
By looking at Page 2 of Scenario 1, how many PHASES of the project have resources that are OVER ALLOCATED?
Group of answer choices
Closing Activities
Executing Activities
It cannot be determined
Executing
Monitoring & Controlling
Planning Activities
Initiating
Initiating Activities
Closing
Planning
Flag question: Question 36
Question 362 pts
By looking at Page 1 of Scenario 2, how many UNIQUE resources have -actionable tasks- that they are assigned to that are ON the critical path? (HINT: don't count the tasks, and don't count any resource more than once.)
Group of answer choices
2
1
3
4
Flag question: Question 37
Question 372 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have ALL of the resources assigned to that task that are fully utilized [100%]?
Group of answer choices
6
8
12
11
10
Flag question: Question 38
Question 382 pts
By looking at Page 2 of Scenario 1, which resource is the most expensive, based on their -Standard Hourly- rate?
Group of answer choices
Designer 1
Analyst 2
QC 3
Driver 2
QC 1
Analyst 1
Project Admin
Project Mgr
Driver 3
QA 2
QC 2
Designer 2
QA 1
Driver 1
QA 3
Flag question: Question 39
Question 392 pts
By looking at Page 2 of Scenario 2, how many -actionable tasks- that are ON the critical path are STILL IN alignment with the baseline? (HINT: milestone tasks are also on the critical path and are always in alignment with the baseline.)
Group of answer choices
4
3
2
1
Flag question: Question 40
Question 402 pts
By looking at Page 2 of Scenario 1, which is the LEAST expensive phase of the project?
Group of answer choices
Executing Activities
Executing
It cannot be determined
Planning Activities
Planning
Closing
Monitoring & Controlling
Initiating
Initiating Activities
Closing Activities
Flag question: Question 41
Question 412 pts
By looking at Page 1 of Scenario 1, how many -actionable- tasks are shown on this page for the project?
Group of answer choices
17
15
16
14
Flag question: Question 42
Question 422 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- are NOT on the critical path [HINT: Milestone tasks are also on the critical path].
Group of answer choices
15
8
9
10
Flag question: Question 43
Question 432 pts
By looking at Page 3 of Scenario 1, how many UNIQUE resources have -actionable tasks- that they are assigned to that are ON the critical path? (HINT: don't count the tasks, and don't count any resource more than once.)
Group of answer choices
3
1
4
2
Flag question: Question 44
Question 442 pts
By looking at Page 2 of Scenario 2, if nothing else changes on the project, will the project finish sooner than the baseline, at the same time as the baseline, or after the baseline?
Group of answer choices
Sooner than the Baseline
It cannot be determined
After the baseline
At the same time as the baseline
Flag question: Question 45
Question 452 pts
By looking at Page 1 of Scenario 1, how many -milestone- tasks are shown on this page for the project?
Group of answer choices
4
1
3
2
Flag question: Question 46
Question 462 pts
By looking at Page 2 of Scenario 2, how many -actionable tasks- that are NOT ON the critical path are STILL IN alignment with the baseline?
Group of answer choices
6
8
11
10
Flag question: Question 47
Question 472 pts
By looking at Page 2 of Scenario 1, which phase of the project is the MOST number of days?
Group of answer choices
Executing
Closing
Planning
Closing Activities
Initiating Activities
Executing Activities
Planning Activities
Initiating
Monitoring & Controlling
It cannot be determined
Flag question: Question 48
Question 482 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have a -Start to Finish- relationship with another task?
Group of answer choices
4
3
2
1
0
Flag question: Question 49
Question 492 pts
By looking at Page 2 of Scenario 1, which is the 2nd MOST expensive phase of the project?
Group of answer choices
Executing Activities
Planning
Monitoring & Controlling
Executing
Closing Activities
Closing
Initiating Activities
It cannot be determined
Initiating
Planning Activities
Flag question: Question 50
Question 502 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have a -Finish to Start- relationship with another task?
Group of answer choices
18
12
16
14
Flag question: Question 51
Question 512 pts
By looking at Page 2 of Scenario 2, how many -actionable tasks- have had some progress made on them?
Group of answer choices
8
11
10
9
Flag question: Question 52
Question 522 pts
By looking at Page 2 of Scenario 1, how many resources do the EXACT same amount of work?
Group of answer choices
3
4
2
5
Flag question: Question 53
Question 532 pts
By looking at Page 1 of Scenario 1, how many -actionable tasks- have no predecessors?
Group of answer choices
2
1
4
3
Flag question: Question 54
Question 542 pts
By looking at Page 1 of Scenario 2, is the OVERALL project currently ahead of schedule, behind schedule, or on schedule?
Group of answer choices
Ahead of Schedule
On Schedule
Behind Schedule
It cannot be determined
Flag question: Question 55
Question 552 pts
By looking at Page 3 of Scenario 2, if nothing else changes on the project, will the project finish sooner than the baseline, at the same time as the baseline, or after the baseline?
Group of answer choices
At the same time as the Baseline
It cannot be determined
After the Baseline
Sooner than the Baseline
Flag question: Question 56
Question 562 pts
By looking at Page 3 of Scenario 1, how many -actionable tasks- that are NOT on the critical path have a resource assigned that is NOT fully utilized (HINT: not working at 100%).
Group of answer choices
3
4
1
2
Flag question: Question 57
Question 572 pts
By looking at Page 2 of Scenario 1, how many PHASES of the project have resources that are NOT OVER ALLOCATED?
Group of answer choices
Initiating Activities
Monitoring & Controlling
Planning Activities
Planning
Closing
Executing
It cannot be determined
Initiating
Closing Activities
Executing Activities
Flag question: Question 58
Question 582 pts
By looking at Page 2 of Scenario 2, how many -actionable tasks- that are ON the critical path are now NOT in alignment with the baseline? (HINT: milestone tasks are also on the critical path and are always in alignment with the baseline.)
Group of answer choices
4
1
2
3

Looking for answers ?